Idaho Public Utilities
Commission
Case No.
PAC-E-10-08, Order No. 32246
May 25,
2011
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website: www.puc.idaho.gov
Commission to hear oral
arguments in wind dispute
The Idaho
Public Utilities Commission has agreed to hear oral arguments between the
developer of four proposed Cassia County wind projects and Rocky Mountain Power
on June 9.
Boise-based
Exergy Development Group is asking for oral arguments in response to a motion
by Rocky Mountain Power to dismiss Exergy’s complaint against the utility.
Exergy maintains
the yet-to-be-constructed wind projects near Malta should be eligible for a
higher rate from Rocky Mountain Power because it submitted a proposed power purchase
agreement with the utility in January 2009, well before the commission lowered a
published rate wind developers receive in March 2010.
Under the
provisions of the federal Public Utilities Regulatory Policies Act (PURPA),
regulated utilities must buy from qualifying small-power producers at a rate
published by state public utility commissions. The rate, called an avoided-cost
rate, is based on the cost the utility avoids by not having to generate the
power itself or buying it elsewhere. Idaho’s avoided cost rate is based on the
cost to generate power at a combined-cycle natural gas plant. When the
Northwest Power and Conservation Council issues a new price forecast for
wholesale natural gas prices, the commission adjusts the avoided cost rate
accordingly. In March 2010, the commission lowered the rate after a council
forecast reflected lower natural gas prices which, in
turn, led to a lower avoided-cost rate paid to small-power producers.
Rocky
Mountain Power filed a motion to have the complaint dismissed, alleging Exergy
did not – and still does not – have the necessary interconnection and wheeling agreements
with Raft River Electric Cooperative and the Bonneville Power Administration
needed to deliver the wind projects’ output to Rocky Mountain Power territory.
Exergy
alleges that securing firm transmission and interconnection rights before creating
a legally enforceable power purchase agreement is not a requirement in Idaho.
Rocky Mountain Power claims that when power must be delivered from off its system
through other entities, some of which are not regulated by the Idaho commission
– such as Raft River Electric – advance agreements are necessary.
Exergy claims it does not have the
interconnection and wheeling agreements because Rocky Mountain Power, during
2009, informed the project that the available transmission capacity from the
proposed delivery point – Brady substation at American Falls – was not enough
to accept more than 23 megawatts of net output from Exergy’s four projects, which,
at full capacity, totaled 70 megawatts. But Rocky Mountain Power reversed
itself in September 2010, Exergy alleges, and said it did have the necessary
transmission capacity for all four projects.
At that point, settlement negotiations resumed. However, they ceased a
few weeks later when Rocky Mountain Power joined with Idaho Power Co. and
Avista Utilities in filing a motion to have the eligibility cap for published
rates reduced from 10 average megawatts to 100 kilowatts.
Exergy is
asking that Rocky Mountain provide detailed explanations for the utility’s
alleged failure to earlier realize that transmission would not be a problem
“and its reliance on that non-existent problem to stall negotiations.”
Rocky
Mountain Power alleges Exergy delayed negotiations by not responding to discovery
requests as to how it planned to deliver its output from the wind farms to the
Brady substation. Further, Rocky
Mountain Power states, Exergy did not file its complaint requesting
grandfathered rates to pre-March 2010 rates until July 29, four months after
the March 16 rate change.
Oral arguments will begin in the commission hearing room, 472 W. Washington St. in Boise, at 9:30 a.m. on June 9. To read more about this case, go to the commission’s Web site at www.puc.idaho.gov. Click on the electric icon, then on “Open Electric Cases, and scroll down to Case No. PAC-E-10-08.