November 22, 2004
BOISE – The Idaho Public Utilities Commission today issued an order defining
the parameters of contracts between Idaho Power and developers of small-power
wind and geothermal projects.
Two
operators of wind power projects and another operator of a geothermal project
in Cassia County filed complaints with the commission earlier this year
alleging Idaho Power is requiring contract terms that are contrary to federal
PURPA provisions.
A
complaint was filed last March by U.S. Geothermal, which owns the 15-megawatt
Raft River Geothermal Power Plant being built in Cassia County. A separate
complaint was filed by Bob Lewandowski, operator of a wind project east of
Boise, and Mark Schroeder, who is developing a wind project in the
Hagerman-Bliss area. The complaints were consolidated by the commission into one
case.
Essentially,
the small-power producers objected to Idaho Power’s contract provisions in
three major areas.
1) Idaho Power proposed to pay
other than the commission-set posted rates when the output from the
complainants’ projects is less than 90 percent or more than 110 percent of
projected output. Idaho Power claimed that when output is less than 90 percent
it must find power from other sources that can be more expensive. When output
is more than 110 percent, Idaho Power said it might have to sell the energy in
the surplus market or reduce output at a more economic generation plant.
The
commission, by a 2-1 vote, agreed to the 90-110 performance band, but allowed
the developers more opportunities to revise their output estimates thereby
allowing them greater likelihood of staying within the performance band. The
commission also lessened the severity of the financial penalties QFs would
receive for falling outside the performance band.
Commissioner
Marsha Smith dissented on the performance band issue. The incentive for all
small-power producers is to provide all they power they can, she said. “They
need to be paid to stay in operation and if they do not produce, they do not
get paid. The banding proposal would operate as a penalty, not an incentive,”
Smith said.
Commission
President Paul Kjellander and Commissioner Dennis Hansen said performance bands
are necessary because both parties of a contract must have reciprocal and
enforceable obligations. To qualify for the commission’s posted rates, QF
projects have an obligation to meet at least 90 percent of their commitment. If
QFs over-deliver there is also a consequence to the company, the majority said.
If unplanned for and not easily integrated, the energy may, as suggested by the
company, have to be sold in the surplus market or other more economic resources
of the company ramped down, the commissioners said.
Idaho
Power had proposed allowing developers to revise their output estimates three
times during the first year of operation and then once every two years thereafter.
The commission ordered that QFs initially provide Idaho Power with one year of
monthly generation estimates followed by estimates every three months.
Further,
the commission revised the financial penalties Idaho Power proposed if QFs fail
to meet production estimates. Idaho Power proposed that QFs that fail to
deliver at least 90 percent pay the difference if the price Idaho Power pays
for replacement power (which would be priced at 85 percent of market price) is
greater than the monthly contract price. Idaho Power agreed to cap the penalty
at 150 percent of the contract rate. Further, Idaho Power wanted to require
that the QF pay for the power Idaho Power would have to purchase to meet the
shortfall if the price of that power exceeded the contract price. The
commission accepted the 85 percent of market price provision but removed the
shortfall penalty.
2) The complainants objected
to Idaho Power’s metered energy test as a method of determining whether a
project qualifies under the 10 MW limit the commission places on the size of
small-power projects to qualify for PURPA rates. Under commission rules, rates
for projects larger than 10 MW are determined on a project-specific basis.
Idaho Power said the 10 MW capacity is exceeded if a QF meter reads greater
than 10,000 kWh per hour. US Geothermal argued capacity should be based on
average annual energy delivered rather than an hourly measure because its
output will vary from 8 MW in the peak of summer to over 12 MW in winter. If
limited to a 10-MW turbine, U.S. Geothermal contends that its Raft River plant
could not deliver close to an average of 10 MW per year.
The
majority on the commission ruled that the 10 MW capacity limit should remain,
but that Idaho Power’s proposed metered energy test is “operationally too
restrictive.” Instead, the commission ordered that QF generation be measured on
a monthly basis, rather than hourly. To qualify for PURPA rates, a QF must
demonstrate that, under normal or average design conditions, the project will
generate at no more than 10 average megawatts in any given month. The
commission also capped the maximum monthly generation qualifying for payment.
Commissioner
Smith dissented, saying capacity should be determined by an annual average.
Idaho Power is protected by contractual provisions that provide a maximum
monthly capacity amount and is not obligated to purchase excess deliveries,
Smith said. “This is nothing more than the status quo that has been available
to all legitimate resources,” she said.
3) The developers objected to
an Idaho Power provision that allowed it to terminate its QF contracts if Idaho
allowed deregulation at the retail level and other parties were able to sell
electricity in Idaho Power’s service territory. Under that scenario, Idaho
Power argued, it would be unable to fully recover its PURPA contract costs. The
commission unanimously agreed to not allow Idaho Power to terminate contracts
if deregulation occurs. “We will not permit Idaho Power to terminate QF
contracts for reasons other than the default of the QF,” the commission
said.
Documents
related to this case can be accessed on the commission’s Web site at www.puc.state.id.us. Click on “File
Room,” then “Electric Cases,” and scroll down to Case No. IPC-E-04-8.
Interested parties may petition the commission for
reconsideration by no later than Dec. 20. Petitions for reconsideration must
set forth specifically why the petitioner contends that the order is
unreasonable, unlawful or erroneous. Petitions should include a statement of
the nature and quantity of evidence the petitioner will offer if
reconsideration is granted.
Petitions can be delivered to the commission at 472 W. Washington St. in Boise, mailed to P.O. Box 83720, Boise, ID, 83720-0074, or faxed to 208-334-3762.
END